July 25: SunCell Pump Modifications on Stations 2 and 3
July 25: Tests were performed on electromagnetic pump modifications of Stations 2 and 3 SunCells. For other stations, vendor electron beam weld errors were worked. The blackbody temperature of the run on 07.24.25 was determined to be 5210K based on the pixel...
July 24: Working on Instrumentation on Station 1.
July 24: Working on instrumentation on Station 1. Inverted black body spectra in pixels by Mightex CCD camera on low input power run. The plasma operated under conditions that are unknown to convectional plasma physis. Worked on changing out SunCells at other...
July 23: Ran Reaction Conditions Tests on Stations 1and 2.
July 23: Ran reaction conditions tests on stations 1and 2.Station 1Station 2
July 22: A five-times start-stop-pause-start cycle
July 22: A five-times start-stop-pause-start cycle was performed and the Suncell was observed to start on demand.
July 21: Video Excerpt of Test Performed on Station 2
July 21: A test was performed on Station 1 and Station 2 in duplicate and gave similar results. This is a video excerpt of the test performed on Station 2.
July 18: Video Excerpt of Test Performed on Station 2
July 18: Video excerpt of test performed on Station 2 that in now operational after some equipment additions. Tests were also performed on station 1 (photo). Very useful data was acquired from both tests as we work through the engineering and hydrino reaction...
July 17: 1min 45s Video
July 17: 1min 45s Video excerpt of test performed on Station 1. No window cavity opacification occurred during this run wherein the dome was not fully cleaned from prior runs. No damage to components or systems was observed. Infrastructure buildout occurring at...
Suncell Update July 16, 2025
July 16: Tests were performed on Station 1 and Station 3.
Suncell Update July 14, 2025
SunCell Update July 14. 2025: Two minute excerpt of today’s Station 3 run regarding a new system at low input power. Cell was stopped to make adjustments. New technology performed very well.
Suncell Update July 13, 2025
We are now routinely running SunCells at four test stations with the goal of an hour continuous run time. These are some of the failure modes that we encountered and fixed with the corresponding forced downtime: vendor bellows weld failure (3 weeks), water pump...
July 25: SunCell Pump Modifications on Stations 2 and 3
July 25: Tests were performed on electromagnetic pump modifications of Stations 2 and 3 SunCells. For other stations, vendor electron beam weld errors were worked. The blackbody temperature of the run on 07.24.25 was determined to be 5210K based on the pixel...
July 24: Working on Instrumentation on Station 1.
July 24: Working on instrumentation on Station 1. Inverted black body spectra in pixels by Mightex CCD camera on low input power run. The plasma operated under conditions that are unknown to convectional plasma physis. Worked on changing out SunCells at other...
July 23: Ran Reaction Conditions Tests on Stations 1and 2.
July 23: Ran reaction conditions tests on stations 1and 2.Station 1Station 2
July 22: A five-times start-stop-pause-start cycle
July 22: A five-times start-stop-pause-start cycle was performed and the Suncell was observed to start on demand.
July 21: Video Excerpt of Test Performed on Station 2
July 21: A test was performed on Station 1 and Station 2 in duplicate and gave similar results. This is a video excerpt of the test performed on Station 2.
July 18: Video Excerpt of Test Performed on Station 2
July 18: Video excerpt of test performed on Station 2 that in now operational after some equipment additions. Tests were also performed on station 1 (photo). Very useful data was acquired from both tests as we work through the engineering and hydrino reaction...
July 17: 1min 45s Video
July 17: 1min 45s Video excerpt of test performed on Station 1. No window cavity opacification occurred during this run wherein the dome was not fully cleaned from prior runs. No damage to components or systems was observed. Infrastructure buildout occurring at...
Suncell Update July 16, 2025
July 16: Tests were performed on Station 1 and Station 3.
Suncell Update July 14, 2025
SunCell Update July 14. 2025: Two minute excerpt of today’s Station 3 run regarding a new system at low input power. Cell was stopped to make adjustments. New technology performed very well.
Suncell Update July 13, 2025
We are now routinely running SunCells at four test stations with the goal of an hour continuous run time. These are some of the failure modes that we encountered and fixed with the corresponding forced downtime: vendor bellows weld failure (3 weeks), water pump...